Meeting of the Parliament 03 March 2026 [Draft]
I engage very regularly with the chief executive, largely, and the chair of Ferguson Marine about the Glen Rosa. I have said to the Parliament before that the priority is to deliver that vessel. Sue Webber will be aware that, with the yard having an additional pipeline of work, there is an even stronger incentive to complete the Glen Rosa on time, because further work is coming.
I note that Ferguson Marine formally advised the Net Zero, Energy and Transport Committee that the target delivery date for the MV Glen Rosa is now quarter 4 of 2026, and that it provided additional information on the cost to complete the vessel, which had increased to £192 million.
I reassure Sue Webber that that engagement happens regularly, but I have often heard it said that, with an additional pipeline of work, the incentive to complete the ship to that schedule increases significantly.