Meeting of the Parliament 14 January 2026
I am sure that the member will have been in the chamber in 2023 when the then cabinet secretary set out the 2023 delivery plan. I reassure him that all the milestones in that delivery plan had been approved. The member is quite right to identify that there has been an adjustment. The Glen Garry to Crubenmore section will go to procurement in 2027, with dualling operational in 2034. That will be a longer period for construction and some of the central sections may take longer. We have to look at what will happen to the Pass of Birnam, depending on the timing and results of any public inquiry, should that happen. The Glen Garry to Crubenmore section will allow us to at least try to get the Dalnaspidal junction into fairly early development. I know that that had been raised previously from a safety point of view.
The remainder of the contracts will be resequenced, but there are benefits within that. I hope that the member can appreciate that we are trying to optimise the remainder of the programme, with completion by 2035.