Meeting of the Parliament 16 January 2025
I will come to you shortly, Mr Ewing.
The report published earlier this week shows that rescheduling and reversing the procurement sequence of the sixth and eighth contracts would result in an expected delay of around a year in the overall completion of the dualling programme. That is due to the need to delay procurement and construction of the fifth contract to avoid an overlap that the current delivery plan was developed to avoid because of the implications for road user disruption. Those changes in the procurement sequence would also reduce continuity of the bidding pipeline for those projects, making them likely to be less attractive to bidders.
I appreciate that there is a range of views about how completion of the dualling programme should be achieved. On that note, I will take an intervention from Mr Ewing.