Two themes have come through loud and clear this afternoon. The first is the litany of failures that have characterised this matter since John Swinney first proudly announced, in 2014, that the SNP would replace 12 ferries for £250 million. Subsequently, that was scaled back to two ferries for £97 million. Those two ferries—the Glen Sannox and hull 802—will not be in service until next year at the earliest.
Those failures include delays in the installation of pipework; up to 939 electrical cable coils that were too short; not installing a ducktail, which reduces resistance and thus fuel use, even though the previous yard owner said six years ago that that was required; not actually running the dual-fuel engines, which now might not even work and are out of warranty—terrifyingly, the minister admitted earlier that he did not even know about that; and not building the bunkering facilities in Ardrossan or Uig that are required for the liquefied natural gas.