Meeting of the Parliament 30 October 2019
I am grateful for the opportunity to take part in the debate today, and I commend the committee for its work and its report.
In February this year, one month before the Culture, Tourism, Europe and External Affairs Committee published its report, I called for a full public inquiry into the fire at the Glasgow School of Art. I was, of course, delighted to see the committee echo in its conclusions and recommendations my call for an inquiry.
We need a full public inquiry for two reasons. First, we need to establish beyond doubt what happened in June 2018, when the Mackintosh building burned down for the second time in four years, and why it happened. Secondly—and every bit as important—we must come to a view about what should happen to the building in the future.
The Culture, Tourism, Europe and External Affairs Committee has done excellent work in identifying a series of unanswered questions, but we now need a properly empowered public inquiry to answer questions about the management and oversight of the Mack’s restoration by the Glasgow School of Art, by the principal contractor—Kier Construction—and by subcontractors. We also need to ask whether appropriate fire safety measures were implemented following the 2014 fire in the building.
The Culture, Tourism, Europe and External Affairs Committee could not get to the bottom of those issues for a variety of reasons that lay beyond its control. Key information remains hidden from the public, despite the committee’s work. Minutes of GSA board meetings have been redacted, as was the Scottish Fire and Rescue Service’s report into the 2014 fire. The principal contractor, Kier Construction, declined to disclose to MSPs on the committee a key document unless it was withheld from the public. A public inquiry would be able to compel disclosure of information, in the same way that a court of law can in normal civil proceedings.
We need an inquiry to answer the following key questions—although this is not an exhaustive list. First, the 2014 fire was put out quickly once the fire brigade arrived, but it had already spread to the top floor by that time. In June 2018, the fire brigade arrived on the scene within minutes of the alarm being raised, but by the time they got there, the whole of the Mack was ablaze, from top to bottom. The SFRS said that the 2018 fire must have been burning for between 45 and 60 minutes before the alarm was raised. How was that allowed to happen?
Between 2008 and 2012, the GSA spent £8.5 million of Heritage Fund money but did not spend money on protecting vents that were critical in accelerating the spread of the 2014 fire. Why?
The Culture, Tourism, Europe and External Affairs Committee was told that it appears to be the case that, in 2018, the GSA had one health and safety officer for the whole estate—not just for the Mack building—and no dedicated fire officer. Is that true?
On Kier’s reconstruction work, why was there no compartmentation, which would have helped to stop the spread of the 2018 fire? If there were people trained to inspect for fire 24/7, as there surely should have been, where were they on the night of the fire, given that the building was ablaze for up to an hour before the fire crews were called? Apparently, the fire and emergency plan set out that there was to be a guard on site overnight and that there was to be 24-hour security monitoring. Why, in June 2018, was no alarm raised until the fire had been burning for an hour?
When asked about the matter by MSPs on the Culture, Tourism, Europe and External Affairs Committee, Kier Construction could not confirm that the fire alarm system had not been switched off in June. That is extraordinary. There had been dozens of false alarms in March, April and May, but none in the three weeks prior to the 2018 fire, and apparently there was no sound of an alarm on the night of the fire. What is the explanation for that?
Those are just five of the questions to which we need answers. They have been identified by Joan McAlpine’s committee, but they have not yet been answered.
Two parties come out of the disaster of the 2018 fire particularly badly. The first is the GSA itself, and the second, I am afraid to say, is the SNP administration at Glasgow City Council. The past 18 months have been profoundly difficult for the businesses and residents of Sauchiehall Street and Garnethill. They have been pushed to breaking point through no fault of their own. I have been deeply struck by their resilience and tenacity.
There was an alarming lack of a coherent and joined-up plan from Glasgow City Council to deal with the consequences of the GSA fire last year. Piecemeal information trickled down to traders and residents in the days and weeks following the fire. It was clear that the council was constantly on the back foot.
Eighteen months on, there is still no long-term strategy for the recovery of Sauchiehall Street. No one blames the council for the fires, but at a time of crisis, it seems that Susan Aitken runs an administration that runs for cover when the going gets tough. SNP councillors right now seem to be more interested in spending taxpayers’ money on shoes for themselves than on helping Sauchiehall Street and Garnethill to recover.
As for Glasgow School of Art’s management, they are even more culpable. Under their stewardship, Charles Rennie Mackintosh’s jewel has been allowed to burn down twice. The Glasgow School of Art has straightforwardly failed in its custodianship of a national treasure. I ask the minister not to allow the management to pull the wool over his eyes. Since the 2018 fire, the GSA’s management have behaved with appalling high-handedness and arrogance towards local residents, with callous disregard for local businesses, and with dismissive disdain towards members of the Scottish Parliament and other elected politicians. They are not fit to run the Glasgow School of Art. They are obstructive and secretive, they are rotten neighbours and they lack any sense of civic duty or responsibility. In my view, the Mackintosh building and its restoration should be taken away from them, and Charles Rennie Mackintosh’s glory should be rebuilt not as a private art school, but as a public asset for us all to enjoy and, indeed, as a magnet to draw tourists from all over the world to Glasgow to celebrate the crowning achievement of one of our finest artists.